Update On Roadwork In Clinton County
- Scott Carney
- Aug 11, 2023
- 1 min read

Crews are rough cutting sub-grade and ditches to create drainage at the new intersection at State Road 28 and County Road 800 W. AT&T completed its relocations on the south side of the project last week. Crews hope to begin installing storm equipment on the north side of the project this week.